Figures / Health and social care / Social care and day care
Delayed hospital discharges: total pathway of care delays and total days delayed, April 2023 onwards
Latest official figures for Bridgend: October 2026.
Area shown by: Local authority of residence.
| Local health board | Reason for delay | Shown as | Bridgend | Wales |
|---|---|---|---|---|
| Wales | Assessment Issues | count of delays | 28 | 541 |
| Wales | Awaiting completion of assessment by social care | count of delays | 10 | 160 |
| Wales | Awaiting completion of assessment Nursing | count of delays | 9 | 67 |
| Wales | Awaiting Continuing Healthcare (CHC) Assessment | count of delays | 1 | 25 |
| Wales | Awaiting joint assessment | count of delays | 1 | 73 |
| Wales | Transfer related issues | count of delays | 1 | 5 |
| Wales | Awaiting hospital arranged transport | count of delays | 1 | 5 |
| Wales | Funding issues | count of delays | 2 | 48 |
| Wales | Awaiting funding decision | count of delays | 1 | 13 |
| Wales | Awaiting funding decision FNC/CHC | count of delays | 1 | 23 |
| Wales | Home care related issues | count of delays | 1 | 127 |
| Wales | Step down to recover and assess | count of delays | 30 | 98 |
| Wales | Awaiting reablement community care package | count of delays | 30 | 91 |
| Wales | Disagreements /Legislation | count of delays | 4 | 69 |
| Wales | Patient / family care home choice | count of delays | 2 | 10 |
| Wales | Safeguarding issues impacting discharge arrangements | count of delays | 1 | 9 |
| Wales | Care Home placement arrangements | count of delays | 7 | 312 |
| Wales | Awaiting care home manager to visit, assess and provide outcome (residential) | count of delays | 1 | 32 |
| Wales | Awaiting care home manager to visit, assess and provide outcome (Nursing) | count of delays | 2 | 28 |
| Wales | Awaiting completion of self-funding arrangements to placement | count of delays | 2 | 20 |
| Wales | Housing Related Issues | count of delays | 3 | 71 |
| Wales | No suitable abode - requires re housing | count of delays | 1 | 16 |
| Wales | Court of Protection Delays - post application | count of delays | 1 | 14 |
| Wales | Total | count of delays | 76 | 1,310 |
| Wales | Awaiting completion of AHP Allied Health Professional Assessment | count of delays | 2 | 44 |
| Wales | Awaiting completion of best interest decision | count of delays | 3 | 79 |
| Wales | Mental Capacity Delays | count of delays | 2 | 30 |
| Wales | Awaiting palliative care community care package (CHC FASTRACK) | count of delays | 1 | 4 |
| Wales | Awaiting palliative care home Care Package (Fast track to Care Home) | count of delays | 2 | 8 |
| Wales | Home unsafe and requires attention | count of delays | 1 | 22 |
| Wales | Awaiting extra care availibility | count of delays | 1 | 2 |
| Swansea Bay | Transfer related issues | count of delays | 1 | 4 |
| Swansea Bay | Awaiting hospital arranged transport | count of delays | 1 | 4 |
| Swansea Bay | Care Home placement arrangements | count of delays | 1 | 29 |
| Swansea Bay | Awaiting care home manager to visit, assess and provide outcome (Nursing) | count of delays | 1 | 7 |
| Swansea Bay | Total | count of delays | 2 | 189 |
| Cwm Taf Morgannwg | Assessment Issues | count of delays | 28 | 92 |
| Cwm Taf Morgannwg | Awaiting completion of assessment by social care | count of delays | 10 | 25 |
| Cwm Taf Morgannwg | Awaiting completion of assessment Nursing | count of delays | 9 | 33 |
| Cwm Taf Morgannwg | Awaiting Continuing Healthcare (CHC) Assessment | count of delays | 1 | 4 |
| Cwm Taf Morgannwg | Awaiting joint assessment | count of delays | 1 | 10 |
| Cwm Taf Morgannwg | Funding issues | count of delays | 2 | 6 |
| Cwm Taf Morgannwg | Awaiting funding decision | count of delays | 1 | 3 |
| Cwm Taf Morgannwg | Awaiting funding decision FNC/CHC | count of delays | 1 | 1 |
| Cwm Taf Morgannwg | Home care related issues | count of delays | 1 | 22 |
| Cwm Taf Morgannwg | Step down to recover and assess | count of delays | 30 | 34 |
| Cwm Taf Morgannwg | Awaiting reablement community care package | count of delays | 30 | 34 |
| Cwm Taf Morgannwg | Disagreements /Legislation | count of delays | 4 | 18 |
| Cwm Taf Morgannwg | Patient / family care home choice | count of delays | 2 | 4 |
| Cwm Taf Morgannwg | Safeguarding issues impacting discharge arrangements | count of delays | 1 | 2 |
| Cwm Taf Morgannwg | Care Home placement arrangements | count of delays | 6 | 47 |
| Cwm Taf Morgannwg | Awaiting care home manager to visit, assess and provide outcome (residential) | count of delays | 1 | 11 |
| Cwm Taf Morgannwg | Awaiting care home manager to visit, assess and provide outcome (Nursing) | count of delays | 1 | 4 |
| Cwm Taf Morgannwg | Awaiting completion of self-funding arrangements to placement | count of delays | 2 | 4 |
| Cwm Taf Morgannwg | Housing Related Issues | count of delays | 3 | 9 |
| Cwm Taf Morgannwg | No suitable abode - requires re housing | count of delays | 1 | 2 |
| Cwm Taf Morgannwg | Court of Protection Delays - post application | count of delays | 1 | 4 |
| Cwm Taf Morgannwg | Total | count of delays | 74 | 232 |
| Cwm Taf Morgannwg | Awaiting completion of AHP Allied Health Professional Assessment | count of delays | 2 | 3 |
| Cwm Taf Morgannwg | Awaiting completion of best interest decision | count of delays | 3 | 9 |
| Cwm Taf Morgannwg | Mental Capacity Delays | count of delays | 2 | 4 |
| Cwm Taf Morgannwg | Awaiting palliative care community care package (CHC FASTRACK) | count of delays | 1 | 3 |
| Cwm Taf Morgannwg | Awaiting palliative care home Care Package (Fast track to Care Home) | count of delays | 2 | 2 |
| Cwm Taf Morgannwg | Home unsafe and requires attention | count of delays | 1 | 4 |
| Cwm Taf Morgannwg | Awaiting extra care availibility | count of delays | 1 | 1 |
| Wales | Assessment Issues | count of days delayed | 1,213 | 14,970 |
| Wales | Awaiting completion of assessment by social care | count of days delayed | 695 | 4,843 |
| Wales | Awaiting completion of assessment Nursing | count of days delayed | 171 | 1,862 |
| Wales | Awaiting Continuing Healthcare (CHC) Assessment | count of days delayed | 107 | 1,065 |
| Wales | Awaiting joint assessment | count of days delayed | 17 | 1,592 |
| Wales | Transfer related issues | count of days delayed | 2 | 200 |
| Wales | Awaiting hospital arranged transport | count of days delayed | 2 | 200 |
| Wales | Funding issues | count of days delayed | 63 | 4,816 |
| Wales | Awaiting funding decision | count of days delayed | 55 | 1,088 |
| Wales | Awaiting funding decision FNC/CHC | count of days delayed | 8 | 1,548 |
| Wales | Home care related issues | count of days delayed | 21 | 4,358 |
| Wales | Step down to recover and assess | count of days delayed | 683 | 1,926 |
| Wales | Awaiting reablement community care package | count of days delayed | 683 | 1,745 |
| Wales | Disagreements /Legislation | count of days delayed | 470 | 5,015 |
| Wales | Patient / family care home choice | count of days delayed | 254 | 748 |
| Wales | Safeguarding issues impacting discharge arrangements | count of days delayed | 145 | 406 |
| Wales | Care Home placement arrangements | count of days delayed | 255 | 21,891 |
| Wales | Awaiting care home manager to visit, assess and provide outcome (residential) | count of days delayed | 77 | 1,718 |
| Wales | Awaiting care home manager to visit, assess and provide outcome (Nursing) | count of days delayed | 64 | 1,297 |
| Wales | Awaiting completion of self-funding arrangements to placement | count of days delayed | 58 | 747 |
| Wales | Housing Related Issues | count of days delayed | 141 | 4,687 |
| Wales | No suitable abode - requires re housing | count of days delayed | 97 | 1,149 |
| Wales | Court of Protection Delays - post application | count of days delayed | 71 | 2,015 |
| Wales | Total | count of days delayed | 2,848 | 58,992 |
| Wales | Awaiting completion of AHP Allied Health Professional Assessment | count of days delayed | 106 | 787 |
| Wales | Awaiting completion of best interest decision | count of days delayed | 97 | 2,573 |
| Wales | Mental Capacity Delays | count of days delayed | 20 | 639 |
| Wales | Awaiting palliative care community care package (CHC FASTRACK) | count of days delayed | 21 | 43 |
| Wales | Awaiting palliative care home Care Package (Fast track to Care Home) | count of days delayed | 56 | 187 |
| Wales | Home unsafe and requires attention | count of days delayed | 29 | 1,059 |
| Wales | Awaiting extra care availibility | count of days delayed | 15 | 239 |
| Swansea Bay | Transfer related issues | count of days delayed | 2 | 172 |
| Swansea Bay | Awaiting hospital arranged transport | count of days delayed | 2 | 172 |
| Swansea Bay | Care Home placement arrangements | count of days delayed | 44 | 3,074 |
| Swansea Bay | Awaiting care home manager to visit, assess and provide outcome (Nursing) | count of days delayed | 44 | 461 |
| Swansea Bay | Total | count of days delayed | 46 | 9,615 |
| Cwm Taf Morgannwg | Assessment Issues | count of days delayed | 1,213 | 3,938 |
| Cwm Taf Morgannwg | Awaiting completion of assessment by social care | count of days delayed | 695 | 1,199 |
| Cwm Taf Morgannwg | Awaiting completion of assessment Nursing | count of days delayed | 171 | 1,105 |
| Cwm Taf Morgannwg | Awaiting Continuing Healthcare (CHC) Assessment | count of days delayed | 107 | 348 |
| Cwm Taf Morgannwg | Awaiting joint assessment | count of days delayed | 17 | 296 |
| Cwm Taf Morgannwg | Funding issues | count of days delayed | 63 | 742 |
| Cwm Taf Morgannwg | Awaiting funding decision | count of days delayed | 55 | 471 |
| Cwm Taf Morgannwg | Awaiting funding decision FNC/CHC | count of days delayed | 8 | 8 |
| Cwm Taf Morgannwg | Home care related issues | count of days delayed | 21 | 678 |
| Cwm Taf Morgannwg | Step down to recover and assess | count of days delayed | 683 | 709 |
| Cwm Taf Morgannwg | Awaiting reablement community care package | count of days delayed | 683 | 709 |
| Cwm Taf Morgannwg | Disagreements /Legislation | count of days delayed | 470 | 2,098 |
| Cwm Taf Morgannwg | Patient / family care home choice | count of days delayed | 254 | 484 |
| Cwm Taf Morgannwg | Safeguarding issues impacting discharge arrangements | count of days delayed | 145 | 173 |
| Cwm Taf Morgannwg | Care Home placement arrangements | count of days delayed | 211 | 3,140 |
| Cwm Taf Morgannwg | Awaiting care home manager to visit, assess and provide outcome (residential) | count of days delayed | 77 | 769 |
| Cwm Taf Morgannwg | Awaiting care home manager to visit, assess and provide outcome (Nursing) | count of days delayed | 20 | 128 |
| Cwm Taf Morgannwg | Awaiting completion of self-funding arrangements to placement | count of days delayed | 58 | 177 |
| Cwm Taf Morgannwg | Housing Related Issues | count of days delayed | 141 | 526 |
| Cwm Taf Morgannwg | No suitable abode - requires re housing | count of days delayed | 97 | 116 |
| Cwm Taf Morgannwg | Court of Protection Delays - post application | count of days delayed | 71 | 638 |
| Cwm Taf Morgannwg | Total | count of days delayed | 2,802 | 12,033 |
| Cwm Taf Morgannwg | Awaiting completion of AHP Allied Health Professional Assessment | count of days delayed | 106 | 108 |
| Cwm Taf Morgannwg | Awaiting completion of best interest decision | count of days delayed | 97 | 651 |
| Cwm Taf Morgannwg | Mental Capacity Delays | count of days delayed | 20 | 123 |
| Cwm Taf Morgannwg | Awaiting palliative care community care package (CHC FASTRACK) | count of days delayed | 21 | 43 |
| Cwm Taf Morgannwg | Awaiting palliative care home Care Package (Fast track to Care Home) | count of days delayed | 56 | 56 |
| Cwm Taf Morgannwg | Home unsafe and requires attention | count of days delayed | 29 | 170 |
| Cwm Taf Morgannwg | Awaiting extra care availibility | count of days delayed | 15 | 15 |
About these figures
The Pathway of Care Delays data identifies patients with a discharge delay, and the reason for the delay, at a given point each month. A delayed discharge occurs when a patient who is clinically ready for discharge cannot leave hospital because the necessary ongoing care and support or suitable accommodation for them is not yet accessible. The data represent the number of adults occupying an NHS hospital bed, who were 'clinically optimised' ready to return home or move on to the next stage of care, that experienced a delay in their transfer of more than 48 hours beyond the point they were clinically optimised. 'Next stage of care' refers to all destinations outside of NHS hospitals. Da